Multan Industrial EstateIssuance of Completion Certificate
- Application for obtaining completion Certificate to be submitted after running factory for 3 months, along with following:
-
- Three sets of as built drawings (Ammonia Prints with owners and architect’s signatures).
- Soft Copy of as Built Drawings on CD.
- Clearance Certificate from EPD.
- Firefighting equipment and network plan with certificate.
- Social Security registration certificate.
- EOBI registration certificate.
- Insurance registration certificate.
- Labor Welfare registration certificate.
- Electrical Industrial Design with sign/stamp by electrical engineer (PEC registered certificate).
- Structure Stability Certificate (as per by-laws).
-
- Case will be scrutinized by BCD department of PIEDMC and visit of factory will be conducted.
- After successful visit, case for issuance of completion certificate will be processed and approval will be obtained from the Competent authority.
- Completion certificate will be issued after approval.